navgurukul / ghar

0 stars 1 forks source link

Reducing donor cycle gap #347

Open its-nasir opened 2 months ago

its-nasir commented 2 months ago

The task is almost complete; only three data are left, which we can easily fill in.

its-nasir commented 2 months ago

Date :- 01/07/2024

I wrote a function for donor gap but that is not worked in some scenarios. Today i will continue with gap related things.

its-nasir commented 2 months ago

Date :- 02/07/2024

I created a form and made some changes to the gap function. After that, Varsha and Shashi pushed the changes to production and tested the donor gap data.

its-nasir commented 2 months ago

Date :- 03/07/2024

Yesterday, we fill some student data for reducing donor gap.

Today, We work on same task.

its-nasir commented 1 month ago

Date :- 09/07/2024

I have filled in most of the gaps in the student gap report, with only 35 gaps remaining. Today, I plan to complete the rest.

its-nasir commented 1 month ago

Date :- 10/07/2024

Today, I will work on 100+ students gaps.

its-nasir commented 1 month ago

Date :- 12/07/2024

Yesterday, I worked on the donor cycle gap and made a sheet of missing placed/dropout students. Today, I will complete the rest of the donor gap data and then remove the extra donor gap changes in Ghar.

its-nasir commented 1 month ago

Date :- 18/07/2024

We have 38 students with missing data in the donor cycle gap. Once the gap sheet is completed, I will fill in the donor gap data for all these students. also today i will connect with poonam for recreate the branch and deploy(Host server) as a dev it's worked or not.

its-nasir commented 1 month ago

Date :- 19/07/2024

I made some changes to the donor Slack notifications. Now, we send them on a weekly basis.

its-nasir commented 1 month ago

Date :- 02/08/2024

I filled some donor gaps, Currently we have 17,18 data pending in donor cycle gap report. Today, i will fill rest of the gaps.

its-nasir commented 1 month ago

Date :- 03/08/2024

I have filled in most of the donor cycle gap data. Only 3 entries are left. Once those are completed, I'll remove the extra changes related to donor gaps from Ghar.