Order from Mooring Systems for Turnaround Cruise January 2018
Have
Need
Item Code
Item
2
2
GCBS-7/8
7/8" galvanized, safety chain shackle, Crosby
2
2
GCBS-3/4
3/4" galvanized, safety chain shackle, Crosby
4
8
GABS-3/4
3/4" galvanized anchor bolt shackle, Crosby
1
6
GABS-5/8
5/8" galvanized anchor bolt shackle, Crosby
1
6
GPL-3/4
3/4" galvanized pear link, Crosby
Notes:
Added pear link and anchor shackle at swivel to be able to break above and below swivel.
Substitute 3/4" anchor shackle for 5/8" shackle to accommodate Hammerhead termination on wire rope, but still have standard termination at other end (just above the swivel) and need one 5/8 shackle.
[x] Determine links and shackles needed and what spares we already have.
[x] What spares do we already have? A: see table above
[x] What size/type of shackle to accommodate the Hammerhead termination? A: 3/4" anchor shackle
[x] Add notes to documentation and drawings for 2018 Turnaround
Order from Mooring Systems for Turnaround Cruise January 2018
Notes:
Added pear link and anchor shackle at swivel to be able to break above and below swivel.
Substitute 3/4" anchor shackle for 5/8" shackle to accommodate Hammerhead termination on wire rope, but still have standard termination at other end (just above the swivel) and need one 5/8 shackle.