To-do list of mobilization items for Shimada:

jrenfree commented 11 months ago
Item Quantity Description Packed?
Serial cable Misc GPS, POS-MV, and K-Sync inputs Have assortment of cables; ET has stock
DB9 connectors 4 each Male and female connectors for serial cables 2 Male; ET has stock
DB9 adapters 4 each Gender changers and null modem adapters 1 F:F; 1 M:M; 1 NM
Cat6e ethernet cable 2 Long cable to run from 18-kHz EK80 PC to WBT, and from EAL to K-Sync 2 cables; ET has stock
Network switch 1 (or 0) For networking computers Yes
Serial Y-cables 4 For splitting GPS, POS-MV, or K-Sync inputs Have 1
Soldering eqpmnt NA For creating custom serial cables ET has
jrenfree commented 10 months ago

The post-survey calibration data from the hake survey has been reprocessed, however the 200-kHz results were quite bad and some oddities were observed in the 120-kHz processing (Echoview has been contacted). But a template .ecs file has been generated that should be adequate.

jrenfree commented 10 months ago

Also processed the pre-survey calibration results in Echoview, and in general it looked as though the post-survey calibration was better. So think it's fine to proceed with processing Leg 4 Shimada data using the post-survey results.

Simrad replied and indicated that the oddities were an issue with Echoview, and game a couple workaround recommendations. Made those changes by the 120-kHz results didn't change much, so will keep the template .ecs file as is.