Book: The Mythical Man Month Ch: 2 The Mythical Man Month #9

Open moziliar opened 2 years ago

moziliar commented 2 years ago

Book: The Mythical Man Month Chapter: The Mythical Man Month

Summary:

Example: Suppose a project is behind the schedule, there are 4 choices to recover from this:

The first two usually don't work as expected, as men-months will be lost in:

Recall Brooks' Law: adding manpower to a late software project makes it later

All in all, the maximum number of men of a project depends on the number of independent subtasks, and the number of months depends on its sequential constraints.