When funds are sent back to Hub at the start of a billing cycle (for non continuous projects), due to delays in cost data being available from AWS/Azure, this is done based on forecasted costs for the final 3 days of the cycle
We should add a mechanism that checks the actual total cost (once it is available & recorded) against that amount sent back to Hub
An alert should be sent to slack if these totals are different
Linked to #44