FU Schedule for each Centre #283

Open marshalc opened 7 years ago

marshalc commented 7 years ago

Produce a schedule per centre, for all the FU events in that centre, and feedback on if the data collection has started, or is complete.

This will also need to feed in to some form of alerting/email system.

Will need to determine how we determine when to schedule FU events because their eligibility windows are going to be too wide for salient reporting purposes. I.e. the reminder for a 12 month follow up will likely need to start appearing at 11 months, but not at 365-65 days, which is when the eligibility window opens for that follow up. Similarly, the chasing up and prioritising of FU events doesn't want to wait until 365+65 for the final follow ups as we want data to be captured within a month for the final event.

marshalc commented 7 years ago

Need to be aware that the physical process for FU data collection varies in each country:

marshalc commented 7 years ago

Awaiting data cleanup to begin this in a sensible fashion