Open dj4oC opened 1 week ago
This is a very big one, it's more an epic than an issue.
Total Priority? expected time to be released?
CC @DeepDiver1975
Take it easy ;-)
In the very first stage I would need an effort estimation on each one. Topic for the next sprint. THX
some estimations about this:
Items priority 1: 30 points Items priority 2: 18 points Items priority 3: 11 points
Total: 59 points
will add specific estimation in individual issues when the work is scheduled
As reference, the average of points achieved in the last 10 sprints is 16. So, 59 points means about 4 sprints as minimum.
As a User I want to be able to perform Space Management on my Android Device.
Prio 1
Prio 2
Prio 3
\cc @DeepDiver1975 @marcelmockkw