Closed ArvickC closed 8 months ago
Base constructed - will be finished 1/15
The stage structure is complete, TBC is attaching the chain and flap/trap. The chain has been ordered and arrived. To be attached according to the CAD. The chain can be found in the cabinet towards the back door, along with the stage structure (kinda hard to miss)—dimensions found in the CAD. Talk to @ArvickC or @SanchitArora44 if questions are present.
Mounting brakets for the chain have been installed. Last step is to attach the chain
Chain has been added, last step is to attach the trap from AM
Vineeth and @KritishAlli began constructing the trap today (2/5). attaching to the stage 2/7
Attached to the stage by @APSo0d and @charlesqing1294
Ordering kit off andy mark