Closed rth closed 2 years ago
As mentioned by @kegl https://github.com/kegl there is a number of changes on master that are still not released, so it would be good make a 0.5.0 release.
The only issue I see is that to be compatible with the server ramp-board would need paris-saclay-cds/ramp-board#533 https://github.com/paris-saclay-cds/ramp-board/pull/533 (I need to check what happened with the CI there). But anyway, I think that it's not an issue, we could
- release ramp-worflow now
- then look into releasing ramp-board and updating the server.
Any objections?
no objection. Just a remark the datacamp course runs till mid march and it would be great to make sure we don't break things during the challenge period. So if there is a risk let's wait for the datacamp course to finish
Message ID: @.***>
Mid March works for me, thx both!
The 0.5.0 release is done. The only thing is I don't have permissions to update the stable
symlink in https://github.com/paris-saclay-cds/ramp-docs/tree/master/ramp-workflow . Could someone do that or give me permissions? Thanks.
As mentioned by @kegl there is a number of changes on master that are still not released, so it would be good make a 0.5.0 release.
The only issue I see is that to be compatible with the server ramp-board would need https://github.com/paris-saclay-cds/ramp-board/pull/533 (I need to check what happened with the CI there). But anyway, I think that it's not an issue, we could
Any objections?