Gantt diagrams close days for someone #26

Closed Gaohaoyang closed 5 months ago

Gaohaoyang commented 5 years ago

I want to try close someday just for somebody, how can I do this? like that:

2019/07/22 to 2019/07/24 is closed on {Joe}
arnaudroques commented 1 year ago

You can have:

@startgantt
project starts on 2020-06-19
[Task1] on {Alice} lasts 10 days
{Alice} is off on 2020-06-24 to 2020-06-26
@endgantt

Does it help?