Problem with planned and remaining hours #17

Closed davinci41 closed 7 years ago

davinci41 commented 7 years ago

The problem appears after editing the task view by the PMI modules Creating a new task and completing Planned Hours does not recalculate.

image

image

After entering the time spent in the task, neither the working time nor the working time are not counted image

sysadminmatmoz commented 7 years ago

I can't reproduce the problem. Setting the planned schedule: screenshot_2017-04-07_13-05-33 Save. Register the work done: screenshot_2017-04-07_13-10-41 Everything is as expected: screenshot_2017-04-07_13-12-35

davinci41 commented 7 years ago

When creating a new task, the remaining time automatically replaces the scheduled time.

I do not complete the remaining time, what more as typing the hours worked it is the remaining time I appear in the minus.

I am using the version available on odoo.com

https://www.youtube.com/watch?v=KgTiGeep8eg

https://www.youtube.com/watch?v=b_hCW__ZVag

https://www.youtube.com/watch?v=lrZtXTH9Rf4

sysadminmatmoz commented 7 years ago

The remaining time is the difference between the planned time and worked time, so it's normal, that with a new task, where the worked time is still 0, the remaining time results the same as the planned time.

The remaining time is not meant to be edited manually except for the reasons of corrections (example: we initially planned less time than needed, so we correct the remaining time when and if we review the task). Don't touch the remaining time field on newly created task.

davinci41 commented 7 years ago

In the default time module, the time worked on the remaining time is redesigned. Https://www.youtube.com/watch?v=TFp4LuCmxTM

After installing PMI differently to the department:

  1. I do not understand why after entering the overworked time the remaining time is in the negative. (After 2 hours of work, 2 hours remaining) Https://www.youtube.com/watch?v=KgTiGeep8eg
  2. I do not understand why it does not change or change without appearing at scheduled times. https://www.youtube.com/watch?v=b_hCW__ZVag
sysadminmatmoz commented 7 years ago

The activity scheduling considers the activity duration field and not the "initially planned hours" since at time it was designed without considering the use of the settings/project option "Manage time estimation on tasks". So to mimic the same functionality as you were used to you just need to set the "Activity duration" field instead of the "Initialy planned hours".

sysadminmatmoz commented 7 years ago

There's another thing to consider: In the tasks (activities) you have 2 planned times (task form, tab other settings).

The Limitations section in that same tab defines the initial calculation data - fill only one of them, depending on your limitations for that task: