Recommended guidance to be added to Project Manager documentation:
Mapping Phase
Limit two mapping projects (<100% Mapped) per campaign[1] as PUBLISHED at MEDIUM or HIGH priority
Any additional projects should remain as DRAFT
As published mapping projects transition to validation, convert standby projects from DRAFT to PUBLISHED
Validation Phase
Reduce priority of 100% mapped projects to LOW priority during validation
No limit on number of projects in validation
Projects at 100% validation must be immediately ARCHIVED
[1] Campaign is defined as a series of related projects on the TM. Multi-state campaigns should be split into separate campaigns by state (i.e. Colorado RR Mapping, Nebraska RR Mapping).`