Power plant labels should be aligned for the merit order chart and table and hourly electricity production #3712

Open mabijkerk opened 3 years ago

mabijkerk commented 3 years ago

The labels for power plants in the chart "Merit order capacities and marginal costs", the table "Merit order table" and the chart "Electricity production per hour", do not align. This can be confusing for users.

For example, the slider Coal conventional has the following labels:

And the slider Onshore inland has the following labels:

I propose to use the same label for each power plant.

github-actions[bot] commented 3 years ago

This issue has had no activity for 60 days and will be closed in 7 days. Removing the "Stale" label or posting a comment will prevent it from being closed automatically. You can also add the "Pinned" label to ensure it isn't marked as stale in the future.

mabijkerk commented 1 year ago

This issue extends to charts where heat is supplied by CHPs, such as the heat network mekko, the properties of combined heat and power (CHP) plants, or the hourly supply of heat to the district heat network. See below for a discrepancy between slider names and labels in the industrial heat network mekko:

Screenshot 2022-12-14 at 12 26 01

I propose to create an overview of all the producers in merit and assign a single label to them, which is then to be implemented throughout the model.

It should be noted that in some cases a slightly different version of the label is required.