Cycle plan: June 28 - July 24 #2049

Closed juliendonck closed 3 years ago

juliendonck commented 3 years ago

This plan captures our work from the week of June 28 till the week of July 24.

Plan Items

Below is a summary of the top level plan items.

Iterations on search

Depending on people search and org search

Navigate to someone else's profile & redesign the profile page

Polish orgs

Test Ethereum features

Iterate on, polish & ship Token Streams


Clean up / nice-to-haves


Engineering tasks


Design tasks


Continuous improvements


Legend of annotations Mark Description
🏃 work in progress
blocked task
💪 stretch goal for this iteration
🎨 design needed
🔵 more investigation required to remove uncertainty
under discussion within the team
a large work item, larger than one iteration