Open rainit2006 opened 5 years ago
7 principles, 7 themes, 7 processes, project environment.
Project:A temporary organization that is created for the purpose of delivering one or more business products according to an agreed business case.
Characteristics of project work : Change,Temporary,Cross-functional ,Unique,Uncertainty
Project management is the planning, delegating, monitoring and control of all aspects of the project, and the motivation of those involved, to achieve the project objectives within the expected performance targets for time, cost, quality, scope, benefits and risk.
Six aspects of project performance to be managed: Costs,Timescales,Quality,Scope,Benefit,Risk
Project Management
Project in context
• continued business justification • learn from experience • defined roles and responsibilities • manage by stages • manage by exception • focus on products • tailor to suit the project.
PRINCE2 requires that for all projects: • there is a justifiable reason for starting the project • that justification is recorded and approved • the justification remains valid, and is revalidated, throughout the life of the project.
Learning from experience takes place throughout PRINCE2:
project management team structure. All projects have the following primary stakeholders: • 'business' sponsors who endorse the objectives and ensure that the business investment provides value for money • 'users' who, after the project is completed, will use the products to enable the organization to gain the expected benefits • 'suppliers' who provide the resources and expertise required by the project (these may be internal or external).
A PRINCE2 project is planned , monitored and controlled on a stage-by-stage basis. PRINCE2 breaks the project down into discrete, sequential sections, called "management stages". The choice of appropriate management stages for a project will depend on a number of factors, including: • the size and complexity of the project (e.g. shorter management stages offer more control, whereas longer management stages reduce the burden on senior management) • significant decisions and control points required during the project's lifecycle; these will often be linked to key investment, business or technical decisions • organizational policies and standards.
In PRINCE2, a project must have at least two management stages: • an initiation stage • at least one further management stage. The more complex and risky a project is, the more management stages will be required.
PRINCE2 enables appropriate governance by defining distinct responsibilities for directing, managing and delivering the project and clearly defining accountability at each level.
Accountability is established by: Delegating authority from one management level to the next by setting tolerances against six aspects of performance for the respective level of the plan: Cost, Time, Quality (quality criteria), Scope, Benefit, Risk
Setting up controls so that if those tolerances are forecast to be exceeded, they are described as being in exception and immediately escalated to the next management level for a decision on how to proceed.
Putting an assurance mechanism in place so that each management level can be confident that such controls are effective.
A PRINCE2 project focuses on the definition and delivery of products, in particular their quality requirements. PRINCE2 requires projects to be output oriented rather than work oriented. PRINCE2 calls these outputs 'products'.
This focus on products: • ensures that the project only carries out work that directly contributes to the delivery of a product; that is, the project does no more work than it needs to deliver its agreed products • helps manage uncontrolled change ('scope creep') by ensuring that all changes are agreed in terms of how they will impact project products and the business justification for the project • reduces the risk of user dissatisfaction and acceptance disputes by agreeing, at the start, what will be produced by the project.
The purpose of tailoring is to ensure that: • the project management method used is appropriate to the project (e.g. aligning the method with the business processes that may govern and support the project, such as human resources, finance and procurement) • project controls are appropriate to the project's scale, complexity, importance, team capability and risk (e.g. the frequency and formality of reports and reviews).
Definition Tailoring:Adapting a method or process to suit the situation in which it will be used.
Organizations adopt PRINCE2 by tailoring it to their needs, often creating their own PRINCE2-based method and then embedding its use within their working practices.
Tailoring can be applied to processes, themes, roles, management products and terminology. The following aspects of PRINCE2 may be tailored: • Processes may be combined or adapted (e.g. by adding or combining activities). • Themes can be applied using techniques that are appropriate to the project. • Roles may be combined or split, provided that accountability is maintained and there are no conflicts of interest. See section 7.2.1.10 for restrictions. • Management products may be combined or split into any number of documents or data sources. They will often take the form of formal documents, but can equally be slide decks, wall charts or data held on IT systems if more appropriate to the project and its environment. • Terminology may be changed to suit other standards or policies, provided it is applied consistently. PRINCE2's principles should not be tailored as they are universal and always apply.
The project manager is responsible for identifying and documenting the level of tailoring for the project. Tailoring affects how a project is managed and so it is documented as part of the PIO, which is reviewed by the appropriate stakeholders and approved by the project board. Both the project board and the project manager may be advised by project assurance, project support roles or a centre of excellence (if one exists).
Team managers (see section 7.2.1.8) may suggest to the project manager any tailoring which would help them manage their work packages more effectively.
Simple projects must adhere to the seven PRINCE2 principles (see Chapter 3); however, the degree of formality for managing the project may be relaxed provided the resultant risk is acceptable.
PRINCE2 management stages can be aligned with a series of sprints or releases, introducing management control points to support a fail fast environment. In situations that have a higher risk or higher uncertainty, the management stages can be of a much shorter duration.
The PID and contract fulfil different purposes. One aspect of a contract is to describe who is liable if either party fails to fulfil its contractual obligations. The content of the PID should focus on practical management arrangements to make sure that each party can fulfil its obligations: the PID must reflect the contract conditions.
When the project is being sponsored by a number of separate organizations, ensure governance is unambiguously defined, especially with respect to who can make which decisions, how risk is allocated and what happens in the case of non-performance.
If a project is part of a programme, take care to ensure that the management products and other documentation are clearly labelled to identify the project, so that readers are not confused as to whether it is a programme-level document or which project within the programme it relates to.
Adopting PRINCE2 in an organization involves two key activities: • tailoring PRINCE2 to create the organization's own project management method • embedding the tailored method by ensuring that people in the organization understand and use it appropriately.
In addition, rather than consider the circumstances of just an individual project, all the projects that the organization typically undertakes need to be considered, together with any other organizational, or externally adopted, policies, processes and practices。
All seven themes must be applied in a project but they should be tailored according to the risk, scale, nature, complexity or simplicity of the project concerned, always ensuring that any minimum requirements specified in a theme are satisfied. Many of the themes imply that procedures may need to be developed: PRINCE2 does not prescribe how these should be documented or published.
The purpose of the business case theme is to establish mechanisms to judge whether the project is (and remains) desirable, viable and achievable as a means to support decision-making in its (continued) investment.
PRINCE2 projects deliver outputs in the form of products, the use of which results in changes in the business. These changes are called outcomes. These outcomes allow the business to realize the benefits that are set out in the business justification for the project.
In PRINCE2, all projects must have a documented business justification. This sets out not only the reason for the project, but also confirms whether the project is: • desirable: the balance of costs, benefits and risks • viable : able to deliver the products • achievable: whether use of the products is likely to result in envisaged outcomes and resulting benefits.
To be following PRINCE2 , a project must, as a minimum:
PRINCE2 requires that two products are produced and maintained for the business case theme:
The development path of business case
The purpose of the organization theme is to define and establish the project's structure of accountability and responsibilities (the who?).
Stakeholder:Any individual , group or organization that can affect, be affected by, or perceive itself to be affected by, an initiative (i.e. a programme, project, activity or risk).
PRINCE2 identifies three principal categories of project stakeholders (business, user and supplier)。