Description of bug

Due to complexity of sequence diagram, including activation bars would make it easier for tracing and understanding the period in which the method is being executed

while i understand that activation bars and return arrows were omitted for minimalism, it was quite confusing for me to trace the diagram without activation bars especially when I had to retrace back some steps

Refer to page 7 of DG sequence diagram for example

Screenshots

image.png

nus-se-script commented 4 months ago

Team's Response

We are afraid that adding activation bars may cause the diagram to be more complicated. and we do not feel the need to have this activation bar as it is direct calls between only 2 classes in each alt case (some 3 classes but the third classes is only being called once).

Items for the Tester to Verify

:question: Issue response

Team chose [response.NotInScope]

Reason for disagreement: [replace this with your explanation]