Name: Jack Hwang ○ 1. What did you work on this past iteration (2 weeks)? Presentation for the demo. ○ 2. What were any major issues/challenges you ran into? N/A ○ 3. What do you plan to work on for this coming iteration (2 weeks)? N/A

sandygoat commented 2 years ago

Name: Sandy Wu ○ 1. What did you work on this past iteration (2 weeks)? Favourite pop-out map components, direction service, Presentation for the demo. ○ 2. What were any major issues/challenges you ran into? N/A ○ 3. What do you plan to work on for this coming iteration (2 weeks)? N/A

fei2223333 commented 2 years ago

Name: Shuge Luo ○ 1. What did you work on this past iteration (2 weeks)? two servers, rabbitMQ ○ 2. What were any major issues/challenges you ran into? setup rabbitMQ ○ 3. What do you plan to work on for this coming iteration (2 weeks)? N/A

Feibulous12 commented 2 years ago

Name: Fei Long ○ 1. What did you work on this past iteration (2 weeks)? Wrote documentation and prepared for the demo ○ 2. What were any major issues/challenges you ran into? N/A ○ 3. What do you plan to work on for this coming iteration (2 weeks)? N/A