Open jipsongeorge2000 opened 5 years ago
Please ensure some employees are already added in the system. Try adding resources using the third tab, directly via Resources.. All added employees will be visible there. Add resources to the project, then maybe add resources to the tasks.
Thank you. That worked. I was able to add employees to projects but while visiting the employee portal the employee is unable to enter time as it shows "no was project assigned".Any idea what could be the reason?
Add tasks to the project, and assign resources to the tasks. Once the tasks are assigned to the resources, they'll be able to enter time using timesheets.
I had created a project and task and then tried to add resources to the task but unfortunately i am not able to see the resource information.It is showing as "resources are not available". I am using version 3.2