Use this template to make a scala-dev ticket named after the release, and fill in the variables.

Variables to be expanded in this template (or set and export them in a local terminal, so that you can copy/paste the commands below without replacing anything):

SCALA_VER_BASE="2.12.18"
SCALA_VER_SUFFIX=""
SCALA_SHA="ceaf7e68ac93e9bbe8642d06164714b2de709c27"
DIST_SHA="2593b53c0d23e58a67c373f2f7347e4a73e3f30d"
SCALA_VER="2.12.18"

Key links:

N weeks before the release

Release announcement / notes

N days before release

Allow time for testing

How much time is sufficient? A week is a bare minimum. Two weeks is a better "normal" amount. We should also respect requests from Scala Center advisory board members, if they explicitly ask for additional testing time. (In the past, we sometimes only waited a day or two, but this was overly optimistic in presuming that people had been testing nightlies all along.)

Be mindful of others' schedules; even minor releases make work downstream (for Scala.js and Scala Native, for the Scala 3 team, for compiler plugin authors, and so on). And a botched release might make unexpected work for ourselves as well as for others. So it's better not to release on a Friday or even a Thursday, or too close to a major holiday. And it's best to release while everyone in both America and Europe is awake. (First thing in the morning in America is a good choice.)

Stage! (point of soft no-return)

Once sufficient time for community testing has passed, it's time to stage the release!

We call this "soft" no-return because even staged artifacts can end up in local caches and cause confusion.

Release! (point of hard no-return)

"Hard" no-return because Maven Central is forever. Also, S3 uploads should be treated as forever (S3 buckets can be changed, but it can takes days to become consistent). Tags, too, should be treated as forever, even though they can technically be deleted and re-pushed.

Check availability

When everything is on maven central

Prepare downstream

Wait for downstream

Before proceeding any further, wait for the ecosystem to catch up.

We have promised to wait 48 non-weekend hours, minimum.

If there are delays downstream, at some point it may make sense to go ahead and announce anyway, since news of the release will already be spreading in the community.

Announcements

Afterwards

You're done!

SethTisue commented 1 year ago

a few steps (SDKMAN, some of the announcements) aren't actually done yet because I'm going to do them for 2.12.18 and 2.13.11 at the same time