Sprint 2 Tasks (Ends March 4th)
Definition: Testing Continued and Start of Implementation
Kickoff meeting:
Team will meet to go over what we got done last sprint and reevaluate any goals or milestones we did or did not meet within the previous sprint. This will be a good opportunity to determine the pace for our project and we will likely have a pretty good idea of what to expect going forward in terms of difficulty/challenges.
Progress Reports each week:
We will continue progress reports at the end of each week, and will maintain bi-weekly reports for Generator as well to keep transparency.
Demonstration at the end of the Sprint:
Will have a good test network to demonstrate at this stage. Should have lots to talk about in terms of challenges we may face or any roadblocks we hit.
Reflection on each Sprint:
Will be writing reflections. What we got done, what we didn't, what we did right and what we did wrong. This is an opportunity to reflect on our workflow and effort we are putting forth.
Sprint 2 Tasks (Ends March 4th) Definition: Testing Continued and Start of Implementation
Kickoff meeting:
Progress Reports each week:
Demonstration at the end of the Sprint:
Reflection on each Sprint:
List of Sprint specific tasks: