Summary:

The task information on the top right does not reset even when the task is no long present on the schedule.

Steps to reproduce:

  1. Click on any task in the schedule to set the information on the top right as such

image.png

  1. Search for a task such that this task no longer appears. E.g. search task cs2103 shows nothing since it does not fully match any word

image.png

The information should no longer be shown to the user since there is a filter/search applied on the tasks and there are no tasks on the schedule.

nus-pe-bot commented 3 years ago

Team's Response

Thanks for spotting! We changed the severity to low because the purpose of deletion is such that it is no longer in the storage. The display acts as a cache and does not affect the user experience and storage correctness.

Items for the Tester to Verify

:question: Issue severity

Team chose [severity.Low] Originally [severity.Medium]