If we do not have a valid quote, or the quote won't last through the PO process (less than about a week or so?), inform the researcher we will need to get the latest quote. Currently JP handles this but I'll see about getting the name of our vendor rep. The vendor name will not be listed in this public repository, you'll have to ask me, JP, or Ralph.
Confirm that the researcher wishes to buy in a ticket in writing. Send them the following information.
The total amount of the quote(s).
The total amount of usable storage. Ask me, JP, or Ralph how to read this. Typically there will be separate hardware and software quotes. The highest-cost line item will have something like 24 x 24TB HDD. Calculate that product and divide by three to get usable storage. In this example 24*24 -> 576 and 576/3 -> 192, so 192 TB usable.
Communicate with our Program Coordinator to process the PO. Send the following info to our program coordinator:
Contact info for the person who handles POs and accounting information on the researcher's side.
Copies of the quotes.
Exactly what is intended to be purchased. Typically this is one of each line item in the quotes, but if in doubt, check with me, JP, or Ralph.
After the PO is committed for purchase, and if we have the storage capacity, increase their storage capacity by the purchased amount. In other words, give them an advance on their purchase.
Inform the researcher when (6) has been completed.
Ops team will install the new hardware after it arrives.
24 x 24TB HDD
. Calculate that product and divide by three to get usable storage. In this example24*24 -> 576
and576/3 -> 192
, so 192 TB usable.