This repo is for community management, including event planning, meeting notes, governance, discussions. Use this repo for everything that is not direct content for the website
0
stars
0
forks
source link
Final report and invoice for DARE funded phase #78
Funded phase ends 31st March, this will require final financial and progress reports.
Actions
[x] Check dates for reports
[x] Write progress report
[x] Update actuals
[x] Create Statement of Expenditure
[x] Request invoice
[x] Send invoice to HDR finance
[x] Send reports to DARE
CG_final_project_reporting.docx
[ ] Progress, successes, issues, and any future plans
Did the project achieve what it set out to? What key activities took place, and were they successful or not? Have there been any project outputs (please share any links to these)? Were there any issues or learnings that you think we as the DARE UK Team need to hear or be aware of? Do you have future plans for the community group?
HDR UK Project Expenditure Report - UK TRE Community.xlsx
[ ] In tab 'Summary'
Please complete your contract reference, project name, project lead (PI), and total award amount from the contract
Total spend will pull through from your detailed report.
At the end of the project, please update row 24 with the total invoiced amount, this should agree with the total reported spend for the project
[ ] In tab 'Detailed expenditure'
Please list all staff funded through this award, noting the FTE, institution, post type (new or existing), and whether or not they are direct programme staff, direct programme support staff or general support staff.
Please list all non- staff expenditure and select whether this is direct, direct support cost or general support
Where relevant, please add any further detail against specific lines
Detail
Funded phase ends 31st March, this will require final financial and progress reports.
Actions
CG_final_project_reporting.docx
HDR UK Project Expenditure Report - UK TRE Community.xlsx
Who can help
No response