Use Evidence-Based Scheduling (EBS) to estimate and manage development tasks, improving the accuracy of project completion timelines.
Description:
This task focuses on using EBS to predict the duration of development tasks. By tracking the actual time taken and comparing it to estimates, the project timeline will be improved. Monte Carlo simulations can be used to predict project completion time based on task factors.
Implementation Plan:
Collect time estimates for each task from team members.
Record the actual time spent on tasks.
Use EBS and Monte Carlo simulations to generate a project completion timeline.
Subtasks:
Gather estimates and actuals for individual tasks.
Perform Monte Carlo simulations to predict project timelines.
Objective:
Description:
Implementation Plan:
Subtasks: