We need to incorporate changes as a result of the feedback given in the full team meeting on the model spec.

We also need to send an email to city liasons with the ability to provide comments and suggestions on the model spec.

This issue can be closed once all comments have been considered and the document has reached a final 'workable' condition.

andymithamclarke commented 4 months ago

This document should be shared with Bunmi - Mary - Taiwo ... unless otherwise specified.

andymithamclarke commented 4 months ago

Friday 22nd - Circulated to WP2/3 Tuesday 26th - Circulated to City Liasons Wednesday 27th - IDEAMAPS Team Meeting Wed 27th - Wed 3rd - @Gtregon to review and incorporate feedback

🚨 FINAL VERSION - Friday 5th 🚨

andymithamclarke commented 4 months ago

@Gtregon - paste link to document here plz

andymithamclarke commented 3 months ago

@Gtregon @gielinkg - can we circulate this document to the full team before the full team meeting tomorrow.

andymithamclarke commented 3 months ago

@gielinkg - Ask Mary to join the team meeting.

Plan B is to find a time to meet with her before the end of the week

Plan C is to send her the document and then ask for review - then looping her feedback in later down the line.

andymithamclarke commented 3 months ago

Updated Dates

Friday 22nd - Circulated to WP2/3 Wednesday 27th - IDEAMAPS Team Meeting Thursday 28th - Circulated to City Liasons - PLAN C - with targetted questions 5th April - deadline for comments 12th April - @Gtregon deadline for incorporation

🚨 FINAL VERSION - Friday 12th April 🚨

Gtregon commented 3 months ago

Deadline changed to 19th April as WP2/3 team had additional feedback. This will be finalised by Friday19th April.

andymithamclarke commented 3 months ago

@Gtregon to send out on Friday

Gtregon commented 3 months ago

UPDATE

Full team draft sent on Friday 19th. Team meeting feedback on 24th.

Gtregon commented 3 months ago

Draft sent to full team on 24th by Grant