ustaxcourt / case-management-rfq

RFQ for Agile Software Development Services
https://ustaxcourt.gov/
17 stars 12 forks source link

Emailed question about transition time #44

Closed JessicaMarine closed 6 years ago

JessicaMarine commented 6 years ago

Regarding “The Court intends to deploy the new System and convert operations from the current system as soon as the software for the new System has been sufficiently developed to provide the minimal functionality required to support the Court’s basic operations.”

Is there an expected timeline for when this would ideally happen?

Is there a defined minimum functionality that would be expected?

JessicaMarine commented 6 years ago

The Court expects to deploy the new System no later than October 1, 2019. The Court currently contemplates a MVP that will include the ability to electronically file documents (including case initiation documents), and the ability for the Court to route those filings to the appropriate internal Court users, take action on those filings, and serve filings and orders on the parties.