Coordinating Institute: NITK Surathkal

Approver’s Name: Dr. Gangadharan K V, NITK Surathkal ( Email: kvganga@nitk.edu.in ) Dr. Pruthviraj U, NITK Surathkal ( Email: pruthviu@nitk.edu.in )

Approved Proposal: The list of experiments for Substation Automation Lab are as follows:**

  1. Circuit Breaker Status Indication from field input:
  2. Control of Group Operated Switches (GOS) from workstation
  3. Monitoring Feeder parameter from workstation
  4. Fault scenario simulation in a feeder
  5. Fault scenario simulation in a Transformer /Bus
  6. Load Transfer from one Feeder to other during Transformer Maintenance
  7. Control Of Bus Voltages Through Onload Tap Changes
  8. Development of 11KV/433 volts substation automation scheme using PLC for normal load operation
  9. Development of 11KV/433 volts substation automation scheme using PLC for timer ON/OFF load control
  10. Development of 11KV/433 volts substation automation scheme using PLC for cyclic ON/OFF load control
  11. Autoreclosure And Sectionalizer Operation

Hosted URL: https://sa-nitk.vlabs.ac.in/

Primary GitHub Handle Details:

Virtual Labs Username: @SOLVE-NITK Gmail: csd@nitk.edu.in

Secondary GitHub Handle Details:

Anusha B Salian Username: @AnushaSalian Gmail: saliananusha1994@gmail.com

Akshaya Username: @AkshayaAcharya Gmail: acharya.akshaya04@gmail.com

@pavanchow

pavanchow commented 2 years ago

@SOLVE-NITK Please find the links for Substation Automation Lab experiments and populate the repositories with sources of the experiments as detailed in Step 4 of the migration document.

  1. Circuit Breaker Status Indication from field input - https://github.com/virtual-labs/exp-circuit-breaker-status-nitk
  2. Control of Group Operated Switches (GOS) from workstation - https://github.com/virtual-labs/exp-group-operated-switches-nitk
  3. Monitoring Feeder parameter from workstation - https://github.com/virtual-labs/exp-monitoring-feeder-parameter-nitk
  4. Fault scenario simulation in a feeder - https://github.com/virtual-labs/exp-simulation-feeder-nitk
  5. Fault scenario simulation in a Transformer /Bus - https://github.com/virtual-labs/exp-simulation-transformer-nitk
  6. Load Transfer from one Feeder to other during Transformer Maintenance - https://github.com/virtual-labs/exp-load-transfer-nitk
  7. Control Of Bus Voltages Through Onload Tap Changes - https://github.com/virtual-labs/exp-onload-tap-changes-nitk
  8. Development of 11KV/433 volts substation automation scheme using PLC for normal load operation - https://github.com/virtual-labs/exp-plc-normal-load-operation-nitk
  9. Development of 11KV/433 volts substation automation scheme using PLC for timer ON/OFF load control - https://github.com/virtual-labs/exp-timer-load-control-nitk
  10. Development of 11KV/433 volts substation automation scheme using PLC for cyclic ON/OFF load control - https://github.com/virtual-labs/exp-cyclic-load-control-nitk
  11. Autoreclosure And Sectionalizer Operation - https://github.com/virtual-labs/exp-autoreclosure-sectionalizer-operation-nitk
pavanchow commented 2 years ago

@SOLVE-NITK @AkshayaAcharya @AnushaSalian

Please click on the following links and accept permissions for repositories.

  1. Circuit Breaker Status Indication from field input - https://github.com/virtual-labs/exp-circuit-breaker-status-nitk/invitations
  2. Control of Group Operated Switches (GOS) from workstation - https://github.com/virtual-labs/exp-group-operated-switches-nitk/invitations
  3. Monitoring Feeder parameter from workstation - https://github.com/virtual-labs/exp-monitoring-feeder-parameter-nitk/invitations
  4. Fault scenario simulation in a feeder - https://github.com/virtual-labs/exp-simulation-feeder-nitk/invitations
  5. Fault scenario simulation in a Transformer /Bus - https://github.com/virtual-labs/exp-simulation-transformer-nitk/invitations
  6. Load Transfer from one Feeder to other during Transformer Maintenance - https://github.com/virtual-labs/exp-load-transfer-nitk/invitations
  7. Control Of Bus Voltages Through Onload Tap Changes - https://github.com/virtual-labs/exp-onload-tap-changes-nitk/invitations
  8. Development of 11KV/433 volts substation automation scheme using PLC for normal load operation - https://github.com/virtual-labs/exp-plc-normal-load-operation-nitk/invitations
  9. Development of 11KV/433 volts substation automation scheme using PLC for timer ON/OFF load control - https://github.com/virtual-labs/exp-timer-load-control-nitk/invitations
  10. Development of 11KV/433 volts substation automation scheme using PLC for cyclic ON/OFF load control - https://github.com/virtual-labs/exp-cyclic-load-control-nitk/invitations
  11. Autoreclosure And Sectionalizer Operation - https://github.com/virtual-labs/exp-autoreclosure-sectionalizer-operation-nitk/invitations
SOLVE-NITK commented 2 years ago

@pavanchow

Ok. Thank you

SOLVE-NITK commented 1 year ago

@pavanchow @priya100raman

When we attempt to access the Substation Automation Lab, we receive a 504 Gateway Time-out error. Kindly requesting you to look at it and rectify the errors.

ravikiran2020 commented 1 year ago

@SOLVE-NITK Issue is fixed. Please check and confirm.

SOLVE-NITK commented 1 year ago

@ravikiran2020

Able to access the lab. Thank you.