Provide an estimate for the completion of this milestone #466

Open travula opened 4 years ago

travula commented 4 years ago

To provide an estimate, test setup is to be created to go through the scenario and assess how many current screens are affected and how many new screens are to be built.

The estimation will take two person days and the deadline is 2020/01/20.

As a rough estimate, the NC workshop snapshot screen should hold also the approved workshops apart from the 'upcoming', 'to be uploaded', and 'pending for approval' workshops.

Once an approved workshop is viewed in detail, the NC should only be able to view the documents but should not be able to upload new documents or delete the existing ones unlike when the workshop is in the other states - 'to be uploaded' or 'pending for approval. This should take 4 person days.

travula commented 4 years ago

20/01/2020

After analysis, there are two problems:

  1. The view button when clicked to view a workshop by an NC does not open the workshop in detail.
  2. Earlier, when the view button was working to view a workshop by an NC,
    only the workshop details are shown but not the documents, This is not the case
    when an OC views a workshop, where the documents are also displayed.

The effort will be 3 person days to fix this.