May 15 Content audit
June 15 Scope, concept, and wire-frames/prototype (need to understand the excluded comment)
July 31 Design
? User testing
July 31 Detailed concept and requirements
Aug 1-Oct 31 Development
July 1-Sep 30 Content
Sep 30 Migration
Oct 31 Testing, bug fixing, etc.
Dec 1 Live
Original suggested deadlines:
May 15 Content audit June 15 Scope, concept, and wire-frames/prototype (need to understand the excluded comment) July 31 Design ? User testing July 31 Detailed concept and requirements Aug 1-Oct 31 Development July 1-Sep 30 Content Sep 30 Migration Oct 31 Testing, bug fixing, etc. Dec 1 Live