Closed aaujayasena closed 5 months ago
Migration Testing Test Plan: Dry Run Phase
Environment
Migration Start Version : 6.1.0 - u2 update
Migration End Version : 7.0.0
DB: Mysql
JDK : 17
Scope:
This test plan covers the verification of migrators during the dry run phase of the migration process for IS 7.00.
The focus is on validating each migrator's execution by comparing the data generated in the old IS version with the results of the dry run.
Migrators as below
Objective:
Test execution
Expected Outcome:
Moving task to another repo. Hence closing the issue.
Is your suggestion a test requirement/change or improvements of the test framework? Please describe. This issue pertains to conducting migration tests on WSO2 Identity Server (IS) 7.0.0 using the migration client too It involves testing the tool and process to ensure a smooth migration experience.
Describe the solution you would prefer Test resources: Migration client Migration resource documents
Useful artefacts:
Test Plan in summery
As part of the initial plan, the first step is to conduct a dry run of the migration process. This phase marks the beginning of our migration testing efforts for IS 7.00. It serves as the foundational phase, laying the groundwork for subsequent testing phases. Following this initial phase, further planning will be undertaken to define and execute subsequent phases of the migration testing process.
Optional Fields
Additional context Issue summery
Document issues
L1
L2
Related Issues: