yanghengtang / pe

0 stars 0 forks source link

Misuse of multiple end nodes in activity diagram #8

Open yanghengtang opened 11 months ago

yanghengtang commented 11 months ago

This activity diagram could have just used one end node instead of 2 end nodes

Screenshot 2023-11-17 at 5.16.16 PM.png

A positive example from another activity diagram would be:

Screenshot 2023-11-17 at 5.38.24 PM.png

soc-se-bot commented 11 months ago

Team's Response

UML notation allows for mutiple end nodes, so we consider this to be a cosmetic issue (VeryLow severity).

Items for the Tester to Verify

:question: Issue severity

Team chose [severity.VeryLow] Originally [severity.Low]

Reason for disagreement: [replace this with your explanation]