What dates are ACTUALLY being used in the extension? #91

Closed ssteiner1 closed 9 months ago

ssteiner1 commented 1 year ago

We thought it was the Start Date and Finish Date. However, when we drag a task to span multiple days on the Sprint Drop Plan board, those dates aren't updated. So are there any dates being used by the extension and if so, what are they? Thanks!

sgtwilko commented 9 months ago

Hi @ssteiner1 You're correct DropPlan does set the StartDate and FinishDate fields on the Task, but just on the task you won't see anything on parent. It's irritating that DevOps will cache the details on the history tab, so if you're going in and out to check what's changed you won't see it until you refresh the browser.