Reselecting Project highlights previously selected task #60

Closed GoogleCodeExporter closed 8 years ago

GoogleCodeExporter commented 8 years ago
1. Select a Project
2. Select a Task that has a Task created above it
3. Select a Different Project
4. Reselect 1st Project

Expect to have previously selected Task under 1st Project, selected upon 
reselecting 1st Project. 
Instead, the Task above it is selected.

Time Tracker 1.3.6
Snow Leopard 10.6.3

Original issue reported on code.google.com by andrewgtibbetts on 4 Jun 2010 at 8:50

GoogleCodeExporter commented 8 years ago
I noticed that too and actually had a fix for it, unfortunately have I started 
with refactoring which now breaks a bunch of other stuff. Need some time to get 
the new version stable before I can roll it out.

Original comment by rbur...@gmail.com on 14 Jun 2010 at 10:35

GoogleCodeExporter commented 8 years ago
should be fixed in 1.3.7

Original comment by rbur...@gmail.com on 5 Jul 2010 at 8:03