Every time GanttProject is opened, the task tree is fully extended, making
browsing difficult if a lot of tasks are present.
1) Can the program extend the tree same as the pattern when the proj…
-
```
Hi,
I will appriciate if you would add Israel holiday calendar.
I know a lot of Israelies that use this application and will be glad for that.
In the meanwhile - is there any way importing holid…
-
```
Even if I really love ganttproject, I cannot use and communicate with this tool
in a big company : it is not a good thing to make advertisements...
I'd like to have the possibility to remove (re…
-
```
It would be valuable to me if there was a visual way to distinguish between
hard and rubber predecessor links. Perhaps the 'rubber' links could be
"squiggly" rather than straight? This would be …
-
```
# One feature per one ticket please
We need provision for adding more roles in the Gantt Chart.
```
Original issue reported on code.google.com by `viva...@gmail.com` on 27 May 2015 at 4:18
-
```
What steps will reproduce the problem?
1. open the file in MS project 2013. no change in day/dates. take screenshot
2.Open the same file in GnattProject 2.7. got change in day/dates
3. Open same f…
-
```
What steps will reproduce the problem?
1. Moving mouse over menu items
2. (The same applies for glyphs within the gantt chart etc.)
What version of the product are you using? On what operating …
-
```
What steps will reproduce the problem?
1.Create new task or highlight existing task name
2.Change task name it return
3.Task name is sometimes changed or may remain as-way
What is the expected ou…
-
```
What steps will reproduce the problem?
1. Create a task of 1 day duration, with any Begin Date: June 14, 2013
2. Check the Milestone checkbox to turn it into a Milestone
What is the expected ou…
-
```
What steps will reproduce the problem?
In the "preview to print" dialog, adjust the start date to any date that is not
the first of the month.
What is the expected output? What do you see instea…