MajesticNerds-orkelljunga-bibliotek
Sprint planning
We are a team consisting of three senior developers. Together we have 30 points to distribute over a two week sprint. One point corresponds to one work day for one developer.
Sprint goal
To integrate and merge current scanners and databases from previous system into the new system.
Definition of Done
- The code has been reviewed and approved by a colleague
- Acceptance criteria met
- Functional tests passed
- Functional tests passed in all browsers
- Simple documentation written
- Merged with dev-branch