agiledigital-labs / probabilistic-forecast

Jira plugin for probabilistic forecasting. (Currently just a command line script.)
MIT License
5 stars 0 forks source link

probabilistic-forecast

Jira plugin for probabilistic forecasting. (Currently just a command line script.)

Type Coverage GitHub Workflow Status

Example Output

Let's say you have a ticket ADE-166 some way down your backlog. Let's say that ticket is in project ADE and the ID of the Jira board (kanban) is 74. ADE-166 represents the completion of a feature that you're interested in. You want to know when that feature will be ready. Here's what you do:

$ JIRA_HOST="example.com" \
> JIRA_TICKET_ID="ADE-166" \
> JIRA_BOARD_ID="74" \
> JIRA_USERNAME=${JIRA_USERNAME} \
> JIRA_PASSWORD=${JIRA_PASSWORD} \
> npm run start
Connecting to Jira and getting board 74.
Counting tickets ahead of ADE-166 in board 74...
There are 86 tickets in board 74 that are either in progress or still to do. Of those, 30 tickets are ahead of ADE-166 in priority order.
Project interval is 2 weeks
The team's past performance will be measured based on tickets in project(s) ADE that have been resolved in the last 5 project intervals (70 days of history will be considered in total).
Resolved 2 tickets in project interval 1:
<snip>
Resolved 2 tickets in project interval 2:
<snip>
Resolved 7 tickets in project interval 3:
<snip>
Resolved 5 tickets in project interval 4:
<snip>
Resolved 11 tickets in project interval 5:
<snip>
1 bug ticket created for every 6.8 non-bug tickets.
1 new non-bug ticket created for every 0.7941176470588235 tickets resolved.
If the team continues to create new tickets at this rate, we predict the 31 outstanding tickets will have grown to 75 tickets by the time they have all been completed.
Running 1000 simulations...
Amount of time required to ship 31 to 75 tickets (and the number of simulations that arrived at that result):
126 days, 0% confidence (5 simulations)
140 days, 3% confidence (29 simulations)
154 days, 8% confidence (53 simulations)
168 days, 19% confidence (111 simulations)
182 days, 35% confidence (158 simulations)
196 days, 50% confidence (146 simulations)
210 days, 65% confidence (152 simulations)
224 days, 78% confidence (128 simulations)
238 days, 87% confidence (93 simulations)
252 days, 93% confidence (56 simulations)
266 days, 97% confidence (43 simulations)
280 days, 98% confidence (14 simulations)
294 days, 99% confidence (8 simulations)
308 days, 99% confidence (4 simulations)
We are 87% confident all 31 to 75 tickets will take no more than 238 days to complete.

Other Environment Variables

Install

nvm use
npm ci

Run

JIRA_TICKET_ID="ADE-166" JIRA_HOST="example.com" JIRA_TICKET_ID="ADE-166" JIRA_BOARD_ID=74 JIRA_USERNAME=foo JIRA_PASSWORD=bar npm run start

See example-run.sh to run interactively.

Debug

NODE_OPTIONS="--inspect-brk" JIRA_HOST="example.com" JIRA_TICKET_ID="ADE-166" JIRA_BOARD_ID=74 JIRA_USERNAME=foo JIRA_PASSWORD=bar npm run start

Then open Chrome dev tools and click the NodeJS icon.

Before Pushing

npm run format && npm run type-coverage