A low priority enhancement I would like is to add an Earliest Date as a pop-up at the Day level when the scheduler goes to select the Scheduled date, which says, "Earliest date recommended is 23/09/2014".This would be calculated from the MAX Earliest Date from the Task against the Day.
Hi Andrew