Open adry-martinez opened 1 year ago
10/9 Discussed with DM and PC regarding creating separate start centers Fog Seal and Sealcoat will be separate with Crack seal underneath. Overlay will also be a standalone for their start center Also consideration for DM to have their designated Start Center to manage
Requesting to track level-ups
requesting to add restriction to SEALCOAT_WORK work orders that requires Length and Width to be required before 4COMP, will need to include CTM in the discussion.
request to change the name of seal coat 2 to fog seal and request to consider a restriction on work orders from being closed-out if pictures are not attached
Find a way to collect information when a project is delayed. Using Specifications tab to say whether this was unproductive or productive, # of days the project was delayed using actual/scheduled time, reason for delay (WEATHER, EQUIPMENT FAILURE, UNDERSTAFFED, ETC)
Actual Start - Scheduled Start can provide the # of days delayed
💠notes only, agenda build out in process)