Project: Maximo Work Order System Discovery #15174

Open maccallump opened 10 months ago

maccallump commented 10 months ago

DTS is researching Street and Bridge Operations’ work order and asset management platform to thoroughly assess its technical capabilities, data quality, user experience, and connected business processes.

Background

The Maximo work order and asset management system is used by the Street and Bridge Operations division to plan and manage their work. The system is used to streamline the workflow, facilitate communication, prioritize tasks, and ensure that work is completed efficiently and on time.

Objective

This Maximo Work Order System Discovery Project will provide a thorough understanding of the organizations' existing system, processes and requirements for the current use of the system. The discovery and assessment will identify opportunities for improvement of potential areas and new integration opportunities. The goal of this project is to identify and assess organizational knowledge and support collaboration between SBO and DTS. Maximo product management and operations collaboration that aligns SBO user needs with the department's goals, while driving efficiency and excellence in the services TPW provides to the community.

The SBO organization has been using the Maximo work order and asset management system for over nine years. The system is currently used to capture 311 service requests, planned maintenance and capital improvement project work for the traditional public works activities, street and sidewalk maintenance, emergency repair work, and transportation infrastructure improvement projects.

The scope of this project includes an assessment of following areas:

The deliverables for this project will be a comprehensive overview of the Maximo systems and processes, identify areas for improvement. offer actionable recommendations for enhancing quality, efficiency, productivity and alignment with organizational goals.

The schedule for the initial discovery for this project is expected to be completed within six weeks. Additional time is needed to develop a roadmap for future enhancements, upgrades and organizational recommendations.

References

Request details

MAXIMO Work Order System Discovery


This Github issue represents a project of Transportation Public Work's Data & Technology Services team. Project status is documented regularly in the comments below.

ChristinaTremel commented 10 months ago

Scheduled Maximo User Process Discovery Meetings with Office of the City Engineer teams:

dianamartin commented 5 months ago

Conducted User Process Discovery Meetings

January

  1. OCE Asset Management
    • Scheduled for 1/18/24 - DONE
    • Stakeholder Attendees: Jonathan R.,
  2. OCE Pavement
    • Scheduled for 1/22/24 - DONE
    • Stakeholder Attendees: Ron K., Reza K.
  3. OCE Right of Way
    • ~Scheduled for 1/24/24~
    • Rescheduled to 2/4/24 - DONE
    • Stakeholder Attendees: William E.

February

  1. District Maintenance - North, Central, South
    • 4A. Central at 9 am
    • 4B. South at 10 am
    • 4C. North at 11 am
    • Scheduled 2/8/24 at Townview - DONE
    • Stakeholder Attendees: Supervisors, superintendents, division managers

March/April

  1. Utilities & Structures/OCE Bridges
    • Met on 3/4/2024 - DONE
    • Stakeholder Attendees: Binaya S., Patty M., Michael D., Charles H.
  2. Utilities & Structures/UER
    • Met on 3/4/2024 - DONE
    • Stakeholder Attendees: John P., Joe H., Michael D.
  3. Utilities & Structures/Concrete
    • Met on 4/1/24 - DONE
    • Stakeholder Attendees: Brad K./Clay R.

April/May

  1. Maximo User Process Discovery - Pavement Ops (Sealcoat)
    • Met on 4/23/24 - DONE
    • Stakeholder Attendees: Fred C., Andre E.
  2. Maximo User Process Discovery - Pavement Ops (Overlay)
    • Rescheduled, there was some schedule conflicts/out of office etc..
    • Met on 5/15/24 - DONE
    • Stakeholder Attendees: Johnathan G., Aaron E.

May

  1. Maximo User Process Discovery - Sidewalk & Urban Trails
    • Met on 5/9/24 - DONE
    • Stakeholder Attendees: Justin Norvell, Austin A.

June

  1. Maximo User Process Discovery - Operations Consulting teams
    • Scheduled for 6/24/24 - NOT STARTED
    • Stakeholder Attendees: Dave A.

6/20/24 - June updates

Synthesizing our notes/feedback

Working on deliverables

image

ChristinaTremel commented 2 months ago

The discovery team is finalizing the Maximo Assessment Discovery Report by detailing what's working, the pain points, and the recommendations/opportunities that we have identified could improve the data quality and user experience for Street & Bridge staff. We anticipate having the report finalized and ready to share within the coming weeks.

We also plan to schedule a meeting with Reiner and team to share our findings and discuss the recommendations that they would like to see us implement moving forward into FY 2025.