Closed ChristinaTremel closed 7 months ago
Participants: Jonathan R, Ron K., Reza K, Rebekka, Adry, Rene, Diana
Ron K - Pavement Operations Engineers
Reza K. - Work in Pavement Mgmt team
Jonathan R. - Asset Mgmt team
Different kind of projects, fog seal, seal coat, crack seal, mill and overlay. Different kind of work
Seal Coat: preparation work - parent work order in
Overlay job
PMIS - Agile Assets
Preparation - to have those Maximo Asset IDs in each project
Send two spreadsheets per treatment (fog seal, seal coat, crack seal, mill and overlay)
Seal Coat: 80% completed projects
Overlay: 50-60%
Crack Seal & Fog Seal: Can get this done for the most part
Spreadsheet that has the 3 lines per work order - this goes into the specifications FROM STREET ON STREET TO STREET
Tracking work orders in Maximo Scheduling of the Service Plans - Excel
Operations
Scheduled Start Date
Scheduled Finish Date Things to change all of those things
Project Coordinator is having to update all that
They are trying to hire more people to help with that administrative work
Maximo can produce a chart, but doesn't show which streets aren't done
Operations was still working on figuring out Statuses
Reza: has been using Maximo to see fiscal year Get reports, filter out using date range - that is very useful
Start Date
happened
Maximo doesn't get total 311 monthly calls for alleys
Pothole can be reported in different ways, for alleys
Report: sbo_alleyresponse.pdf
Maximo doesn't compile data on a daily basis
Daily Log, originally set up as Excel spreadsheet
On Actuals tab Material information can be tracked, but not in very much detail Asphalt - Type C mix, different recipes
Contractor overlay work - that is in Maximo as well Fog Seal - contractor In general, if a project is specific location. Traffic is challenging, sometimes they contract that work on a case by case basis Manage the contractors
How does your team use MAXIMO?
Reza RE: work with Pavement Management OCE with MAXIMO
Service Plan Creation
Permitting Process
proactive/planned work is loaded
in MAXIMO, instead of manually added. consistent and mandatory
entry for the fields we need for Work Orders.
Thoughts: Which fields are currently mandatory or have restrictions, to aid to consistent records. remove all spreadsheet
components of their process? Request examples of all spreadsheets they use to track. track and account for travel time
and the effects on productivity
Thoughts: Are there any GIS features or travel time data that could support this? Legacy Pavement Discussion Documents from Ecosystem Sessions #12893
@ChristinaTremel are you needing to add your notes?
Can we add an agenda item about reports? “What reports or “spreadsheets” do you use from Maximo? What do you do with that report/spreadsheet?
@maccallump are you talking about adding those questions to the assessment board we have? We have these questions we ask
Notes were added to the miro board ✅
Objective
The Data & Technology Services Division is initiating a series of meetings to learn more about Maximo user experiences and processes in TPW. In this meeting we'll be asking questions about how individual teams use Maximo and how it fits into their work processes.
Participants
Goals:
Agenda
User experience and interface experiences
PROCESS - Planning
PROCESS - Implementation
PROCESS - Field Work
Maximo system performance and functionality
PROCESS - Review & Reporting
User feedback and improvement
Future roadmap and upgrades
Points of Contacts