Closed ChristinaTremel closed 4 months ago
Feb. 8. 2024 Users requested
ATD Markings
, MARKINGS_TYPE
, TABS PLACED
Daily Activities Report
to remember what they did in the field (on the sheet of paper)Daily Activities Report
into the office and fill out the Maximo ticket at the shopDaily Activities Report
and take photo on their phoneDaily Activities Report
into the office and fill out the Maximo ticket at the shop
4COMP
(as long as the work order is done at the end of that day)CSR Work
Newly Screened District Work Orders
widget on Maximo start centerActive Work Orders Owned By Me
Owner/Lead
and change the status to In Progress
Alligator Cracking
- this is a failure that the subgrade is not compacted properly, water seeped through, and it starts failingPavement Failure
some times and Damaged Pavement
FLEX FIELD 2
(this is a temporary repair)
4COMP
(Completed), Supervisors 4COMP-NFR
(Needs Final Review), and Superintendents do 4QACOMP
(Closed)
Type
field and select status to close out CSR
Flex Field 2
to Acknowledged By Receiving Group
Standby
Other ways to receive work
Supervisors
if they see an issueFlex Field 2
Flex Field 2
?
Reactive Work
Comes in as a SR
Mike, Shon, Corey
Start
SR Created
Sent to interface
OCE Dispatch will convert (regular business hours, M-F)
“Stand by crew” - On Call
North - “Junior”
Central - Mike/Shon/Corey (one lead for that crew)
South - Eli
Superintendent looks at it, Shon (supervisor) looks at it
Monday (CSRS from the weekend)
Most calls are about 15 minutes within one district
District Maintenance - other groups investigate (AE, AW)
Investigation: over 550 (2.5 month period)
Start responding on work
Self assignment - “Owner/Lead” field
Manually change status - 2INP IN PROGRESS
In the Field
Superintendents creates new parent work
Queues - lots of tickets to review (1800)
Every person should be Maximo everyday
So you have to select work log in Work Order to close out SR
Overnight emergency
permit
Mi-Fi’s
Only 1% of techs doing work in the field
Laptops
Maximo job description
Notes have been added to the miro board! Closing this. ✅
Objective
The Data & Technology Services Division is initiating a series of meetings to learn more about Maximo user experiences and processes in TPW. In this meeting we'll be asking questions about how individual teams use Maximo and how it fits into their work processes.
Participants
Goals:
Agenda
User experience and interface experiences
PROCESS - Planning
PROCESS - Implementation
PROCESS - Field Work
Maximo system performance and functionality
PROCESS - Review & Reporting
User feedback and improvement
Future roadmap and upgrades
Points of Contacts