Open adry-martinez opened 8 months ago
Patti M., Rene V., Adriana M.
see Agenda
Maximo team:
Bridges: none at this time.
Next meeting scheduled for March 27, 2024.
Patti M., Clay R., Adriana M., Diana M.
Work Group assignment to reflect MORENOP and ELLISONJ for SBOBRIDGE and for SBOMOBTRL.
Previously discussed when District Maintenance received a work order, a call from WPD cleaning out a culvert in the creek. Called in the broken bridge rail, no one has fixed it, forwarded over to Patti, District had been out there, put a cone and closed it; not forwarded to Bridge. I advised that currently on the Bridge start center there is the work group notification portlet, I demo'd flex field 2 to Patti. I will need to send her the QRG for this process.
Calls received by different channels, Patti wants to have those calls counted. I advised using requesting agency to help facilitate that count.
Clay wanted a Concrete start center. Team to schedule meeting with Clay and Brad to discuss design. Clay needed assistance to update UER start center to see updated report list.
Next meeting scheduled for April 24, 2024
Clay R., Rebekka, Rene, Adriana Patti was not available due to TPW Supervisor Meeting
DTS Maximo
Bridge none at this time
Next meeting scheduled for two weeks: May 15, 2024 meeting re-scheduled to May 29, 2024
Ganesh, Clay, Patti, Rebekka
📝 Please see each above reference link for additional notes 📝
DTS Maximo
USD - Bridges
MAXIMO filter, search bridge and conc
💡
Row Labels | Count of Pipeline |
---|---|
Icebox | 1 |
In Progress | 1 |
Needs Scoping | 2 |
On Deck | 1 |
Ongoing | 1 |
Clay, Rebekka, Adry, Ganesh, Rene
📝 Please see each above reference link for additional notes 📝
DTS Maximo
📝 Please see each above reference link for additional notes 📝
DTS Maximo
keep agenda for next meeting Patti OOO until July 16th
Rebekka and Ganesh
📝 Please see each above reference link for additional notes 📝
DTS Maximo USD: Bridge
Currently not using forms for tracking
Create own work orders (some times through 311, or OCE - moving forward they will not be creating
OCE - report from TXDOT bridges; moving forward BRD will review and decide which are made priority
Work Group:
Priority determined? - Ah Yong follow up
Large and Small currently determined by dolloar amount (not sure how we get there now, maybe over 5K over a week)
Actual and specifications - as we complete (not daily) [need to train a few people on data entry]
24-176077 - example of OCE
24-167878
🚥 OCE not putting work orders in anymore? amount of outstanding tickets. Patti uses a way to track work orders that need to be handled. Concern about duplicate tickets, if OCE finds and BRD finds. The process has been going back and forth. What is the frequency of their report submission? Varies. They would like to have roll over like PAVE SLCT where needed like a service plan, once or twice a year.
PMIS - pavement conditions data imported to
What could be used to support Service Plans needs. TxDOT - provide report BDG - system that keeps reports for all the bridges and system calculates what needs to happen on the system
Statuses need to decide
2APR 2ONHOLD - being looked at / engineering issue
3INPROGRESS - when working on it
Tag Asset No asset IDs tied to BRD. linked to service address. Has lat and long. Currently do not segments to determine exact working area (ex 100ft, only working 10ft) Descriptive Measures: Span 3/Beam4/NorthBound/Outside Lane
TO DO
📝 Please see each above reference link for additional notes 📝
Additional Questions BRIDGE_WORK - classification Types of Service Types: Materials required, specifications known for each? = what is being reported on for Bridges?
DTS Maximo USD: Bridge
MIRO MAPPING OF CURRENT BRIDGE PROCESS 8/9/24 https://github.com/cityofaustin/atd-data-tech/issues/13542
scheudle another mapping meeting. follow up with DTS apps for solution
Miro Board https://miro.com/app/board/uXjVKksGZEo=/
TxDot Report Sample 14-227-0113-12-090_RTInsp_2024-02 (1).pdf
Bridge Processing Video Part 1
Bridge Current Reporting SBO Performance Report 2024.07.25 1.pdf
📝 Please see each above reference link for additional notes 📝
Additional Questions BRIDGE_WORK - classification Types of Service Types: Materials required, specifications known for each? = what is being reported on for Bridges? Any alignment with the Inspection Report data?
DTS Maximo
USD: Bridge
Objective
This meeting is to discuss any ongoing Maximo projects and support for the Bridges work group.