Pavement: Updated Work Order Checklist #16771

Open rebekkabry opened 6 months ago

rebekkabry commented 6 months ago

Background

In preparation for Pavement Training - we found a few updates that could be used on the work order completion checklist.

16288

image

Items To Do

NEW

MODIFICATIONS

rebekkabry commented 5 months ago

4/25/24

rebekkabry commented 5 months ago

5/13/24

Work session to discuss Seal Coat prep and post children work order completion needs.

NOTE: All Parent Work Orders are imported with 3 related children workorders (Prep:LU, Prep:SW, Prep:CS)

NOTE: All specification needs and requirements are different. Currently no work order checklist or documentation for phases.

1. Level Ups Phase

2. Crack Seal Phase performed by Crack Seal team NOTE: there is no measurement for this. they have not come to a point of what is being used, maybe gallons; but not there yet.

3. Seal Coat Phase NOTE: Parent work order can not be closed at completion, because sweeping child must be completed first. Once above complete, the Parent work order is now worked on by the Seal Coat team. Following the original work order completion checklist

4. Sweeping Phase

rebekkabry commented 5 months ago

Next Steps:

rebekkabry commented 5 months ago

5/`15/24 Additional Notes

https://miro.com/app/board/uXjVKI0wi4c=/