Open TracyLinder opened 3 years ago
I removed the Project Index
label from this pending the missing info.
@TracyLinder work on cleaning this up & scheduling regular project meetings.
A project kick-off has been scheduled for Wednesday April 14, 2021. We will refine the scope, assign project members, and plan logistics.
Issue #5734
Attendees: Tracy, Nate, Vish, Ryan, Paloma, Izzy
Why are we doing this, what problems might we solve?
What will make this project fail; what are your concerns?
In Scope
Out of Scope
Sprint Logistics:
Communications:
Tracy Will:
Metrics need to be collected for all permit folders: RW, DS, EX, PSM
Core Team Mtg 5/12/21
Discussed Vish's analysis of current permit workflows:
Discussed Possible Solutions:
I made an issue to document notes from our biweekly project meetings. See #6218
This project was placed on hold in Aug 2021 due to the FY23 fee update project and then for the AMANDA V7 and Portal upgrade projects. This project needs to be prioritized with ROW again. I spoke with DTS' Data Science team about this today and asked Charlie to join me in a meeting with ROW next Monday 6/5/23.
P: This is a big project - should we wait for ECM before trying this? Still a need - consider that it will be replaced so the solution won't last for more than 1-2 years.
D: Does DSD's expansion of PDox affect this at all? UC, GP - They're in UAT and training now. A: Wherever the data lives, we'll need to grab it there.
ROW has an interum assistant director; now is not the best time to prioritize backlog project until the new AD is settled in and ready to review IT Projects.
Performance metric data continues to be a high priority for ROW. The best solution is a new permitting system which is being procured as part of the ECM Replacement. Given our constraints we've altered our approach by prioritizing sprint sized work that improve performance data collection and reporting. Our data science team has provided ROW with a performance dashboard that is updated to accommodate new data points as they are added to ROW's workflows.
This project index is likely to stay in the backlog, with the deliverables instead being implemented with the new permitting system. ROW leadership requested that we leave this index in our backlog as it does represent an unmet high priority need.
Enhancements to the AMANDA permitting system to 1.) Capture Right-of-Way permitting metrics data, and 2.) Create all AMANDA reports requested by ATD Executive Management.
Background
ATD Executive Management has requested a series of AMANDA reports related to Right-of-Way permitting and has identified 4 major reporting metrics. Unfortunately the majority of the data required for this reporting does not currently exist.
Scope & Deliverables
There will be two (2) phases of development.
Timebox
From kickoff to delivery, we estimate this project will take 4 – 6 months.
Phase 1: AMANDA Enhancements
Phase 2: Custom Reports
This Github issue represents a project of Austin Transportation's Data & Technology Services team. Project status is documented regularly in the comments below.