eProcurement-everis / ePO

2 stars 0 forks source link

AP for NM - 22/03/2018 #25

Closed sembu-eproc closed 6 years ago

sembu-eproc commented 6 years ago

7 | Send everis a new version of the e-Forms BT. | 04-04-2018 | NM

8 | Send an official confirmation to everis about the roles re-distribution proposal from February MCR, as a mitigation plan of Enric’s lack of time. | 04-04-2018 | NM

9 | Set the configuration of the issues in Wiki to "Watching", to receive notification emails. | 04-04-2018 | NM

muricna commented 6 years ago

NM answer

7) A new version of the eForms BT will be sent at a later date. However please make sure that the version validated at the end of the last contract is the only version visible to the working group.

8) Since the offer did not provide information on how the work was sub-divided, this is an internal issue for everis the deliverables foreseen for the project should be provided at the end of the project without there quality being put at risk - I will reply this also in my comments to the monthly report. 9) I have reset the watching