Assistant | 1st S.P Role | 2nd S.P Role | 3rd S.P Role |
---|---|---|---|
Jeongyun Lee | Scrum master | UI Developer | UI Developer |
Marc Visa | General Expert | Scrum Master | General Expert |
Ronnel Mathew | Financial Expert | Financial Expert | Financial Expert |
Eyad Al Hafi | Developer | Backend Developer | Scrum master |
Presentation Idea Presentation | 1st Presentation | 2nd Presentation | 3nd presentation | [Final Presentation] |
Sprint | MON | TUE | WED | THU | FRI |
---|---|---|---|---|---|
1st | 19 | 20 | 21 | 22 | 23 |
1st | 26 | 27 | 28 | 29 | 30 |
1st | 2 | 3 | 4 | 5 | 6 |
2nd | 9 | 10 | 11 | 12 | 13 |
2nd | 16 | 17 | 18 | 19 | 20 |
2nd | 23 | 24 | 25 | 26 | 27 |
3rd | 30 | 1 | 2 | 3 | 4 |
3rd | 7 | 8 | 9 | 10 | 11 |
3rd | 14 | 15 | 16 | 17 | 18 |
3rd | 21 | 22 | 23 | 24 | 25 |
๐นSprint Plan & Report & Retrospective
Sprint Explanation |
1st sprint report |
1st sprint retrospective |
1st sprint review |
2nd sprint planning | 2st sprint report | 2nd sprint retrospective | 2nd sprint review | Sprint2 app full video |
3rd sprint planning | 3rd sprint report| [3rd sprint retrospective] | 3rd sprint review
Report of used tools and libraries | Demo video | Demo survey video |
๐นTechnical Model
DB model |
DB model documetation |
MOCK UP |
General System Architecture |
Admin part report
๐นETC
Use Case Diagram |
Use Case Description |
User stories |
Financial model |
Financial explanation |
Sprint | Date | Task | PIC | Effort Point | status |
---|---|---|---|---|---|
16 tasks | 62 in total | ||||
1 | 19 OCT- 09 NOV | Sprint meeting managing | Yoon | 2 | Done |
1 | 19 OCT- 09 NOV | Presentation resource & presentatin | Yoon | 5 | Done |
1 | 19 OCT- 09 NOV | Sprint explanation | Eyad | 2 | Done |
1 | 19 OCT- 09 NOV | General Service Architecure | Yoon | 3 | Done |
1 | 19 OCT- 09 NOV | Mock up | Yoon | 5 | Done |
1 | 19 OCT- 09 NOV | Finantial model | Ron | 8 | Done |
1 | 19 OCT- 09 NOV | Looking for Alternative DB resource | Yoon | 3 | Done |
1 | 19 OCT- 09 NOV | DB data model | Marc | 5 | Done |
1 | 19 OCT- 09 NOV | F0 : sign up with username / pw | Eyad,Marc | 2 | Done |
1 | 19 OCT- 09 NOV | F0 : sign in with username / pw | Eyad,Marc | 2 | Done |
1 | 19 OCT- 09 NOV | F0 : sign in with Google account | Eyad,Marc | 2 | Done |
1 | 19 OCT- 09 NOV | F0 : sign in with Facebook account | Eyad,Marc | 2 | Done |
1 | 19 OCT- 09 NOV | F1 : start menu | Eyad,Marc | 3 | Done |
1 | 19 OCT- 09 NOV | F1 : search pill (search bar) | Eyad,Marc | 8 | Done |
1 | 19 OCT- 09 NOV | F1 : print pill info (description page) | Eyad,Marc | 5 | Done |
1 | 19 OCT- 09 NOV | F1 : List up pills | Eyad,Marc | 5 | Done |
17 tasks | 71 in total | ||||
2 | 10 NOV- 25 NOV | PBI & Sprint Backlog managing | Marc | 2 | DONE |
2 | 10 NOV- 25 NOV | Admin report | Marc,Eyad | 5 | DONE |
2 | 10 NOV- 25 NOV | Scrum Planning | Marc | 2 | DONE |
2 | 10 NOV- 25 NOV | Scrum Review - 1st sprint | Yoon | 2 | DONE |
2 | 10 NOV- 25 NOV | Scrum Retrospective - 1st sprint | Yoon | 2 | DONE |
2 | 10 NOV- 25 NOV | Update General Architecture | Yoon | 5 | DONE |
2 | 10 NOV- 25 NOV | Update database model documentation | Ron | 5 | DONE |
2 | 10 NOV- 25 NOV | Update the use case diagram | Ron | 1 | Done |
2 | 10 NOV- 25 NOV | Update the cashflow excel | Ron | 5 | DONE |
2 | 10 NOV- 25 NOV | Update Financial documentation | Ron | 3 | DONE |
2 | 10 NOV- 25 NOV | Presentation resource & presentation | Marc,Yoon | 5 | DONE |
2 | 10 NOV- 25 NOV | F2: set sleep time for alarm | Eyad | 5 | DONE |
2 | 10 NOV- 25 NOV | F2 : setting alarms | Eyad | 8 | DONE |
2 | 10 NOV- 25 NOV | F2 : pill box | Eyad | 3 | DONE |
2 | 10 NOV- 25 NOV | Connection to API | Eyad | 8 | DONE |
2 | 10 NOV- 25 NOV | F3 : notification with pop up | Yoon | 8 | DONE |
2 | 10 NOV- 25 NOV | F3 : noti scenario | Yoon | 5 | DONE |
20 tasks | 62 in total | ||||
3 | 30 NOV- 22 DEC | Sprint meeting managing | Ron,Eyad | 2 | DONE |
3 | 30 NOV- 22 DEC | Presentation resource & presentatin | Marc,Yoon | 8 | DONE |
3 | 30 NOV- 22 DEC | Scrum Planning | Eyad,Marc | 1 | DONE |
3 | 30 NOV- 22 DEC | Scrum Retrospective - 2nd sprint | Marc | 1 | DONE |
3 | 30 NOV- 22 DEC | Scrum Review - 2nd sprint | Marc | 1 | DONE |
3 | 30 NOV- 22 DEC | DEV : Improve the GUI | Yoon,Eyad | 13 | DONE |
3 | 30 NOV- 22 DEC | DEV : Merge the code (function) | Eyad | 2 | DONE |
3 | 30 NOV- 22 DEC | F2 : Running the Alarms | Eyad | 8 | DONE |
3 | 30 NOV- 22 DEC | F2 : Set sleep time for alarm | Eyad | 5 | DONE |
3 | 30 NOV- 22 DEC | F2 : saving alarm list in firebase | Eyad | 2 | DONE |
3 | 30 NOV- 22 DEC | F2 : Delete alarm function | Eyad | 2 | DONE |
3 | 30 NOV- 22 DEC | F3 : Create the survey form | Eyad | 1 | DONE |
3 | 30 NOV- 22 DEC | F3 : Create notification scenarios | Yoon | 2 | DONE |
3 | 30 NOV- 22 DEC | F3 : Connect the noti with user info | Yoon | 5 | On going |
3 | 30 NOV- 22 DEC | DOC : Update data diagram model | Ron | 2 | DONE |
3 | 30 NOV- 22 DEC | Doc : Update General Archecture doc | Yoon | 1 | DONE |
3 | 30 NOV- 22 DEC | Doc : Update the financial factor doc | Ron | 2 | DONE |
3 | 30 NOV- 22 DEC | Doc : Design the app logo | yoon | 2 | DONE |
3 | 30 NOV- 22 DEC | Doc : update the use case doc | marc | 1 | DONE |
3 | 30 NOV- 22 DEC | Doc : Report api & libraries | Eyad | 1 | DONE |
[Function 0 : Sign up & Sign in]
[Function 1 : Searching pill with name / characteristic]
[Function 2 : setting alarm & pillbox]
[Function 3: notification]
[Backend]
[Scrum & Project Managing]